Jump to main content.


Funding Resources

Funding Resources
CT Interconnection Standards
Type of Incentive Interconnection
Eligible States CT
Eligible Technology Backpressure Turbine, Boiler, Combustion Turbine, Condensing Turbine, Extracting Turbine, Fuel Cell, Microturbine, Other, Reciprocating Engine, Heat Recovery Generator, Stirling Engine
Eligible Fuel # 2 Fuel Oil, # 6 Fuel Oil, Biogas, Biomass, Coal, Hydrogen, LFG, Municipal Solid Waste, Natural Gas, Other, Tire-Derived Fuel, Waste heat Recovery
Eligible Project Size < 20 MW
Critical Information Eligible Technologies: Photovoltaics, Landfill Gas, Wind, Biomass, Hydroelectric, Fuel Cells, Municipal Solid Waste, CHP/Cogeneration, Microturbines, Other Distributed Generation Technologies Size Limitations: 20 MW External Disconnect Requirements: Yes Insurance Requirements: Yes, Varies by system size and/or type; levels established by commission.
Start Date 4/30/2004
End Date

 

Minimum Efficiency (%)

 

Additional Information Connecticut's interconnection guidelines, approved in December 2007, apply to Connecticut Light and Power Company (CL&P) and United Illuminating Company (UI) and are for distributed energy systems up to 20 megawatts (MW) in capacity. The guidelines are modeled on the Federal Energy Regulatory Commission's (FERC) interconnection standards for small generators, and like FERC's standards, include provisions for three levels of systems:

(1) Certified, inverter-based systems no larger than 10 kilowatts (kW) in capacity;

(2) Certified systems no larger than 2 MW in capacity; and

(3) All other systems no larger than 20 MW in capacity.
Web Site http://www.cga.ct.gov/2011/pub/chap283.htm#Sec16-243a.htmExit EPA
Additional Web Site http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=CT06R&re=1&ee=1Exit EPA
Primary Contact John Buckingham
10 Franklin Square
New Britain, CT 06051
U.S.A.
John Buckingham (john.buckingham@po.state.ct.us)
(860) 827-2891

Top of Page


Local Navigation