Fiscal Year 2008 BRAC Program Snapshot

PowerPoint Version (2 pp, 92K)

On this page


BRAC Federal Facilities by BRAC Round

BRAC 1: 18% (19), BRAC 2: 24% (26), BRAC 3: 26% (28), BRAC  4: 32% (34)

Top of page


NPL Status of BRAC Facilities

NPL Status Number of BRAC Facilities
Proposed 3
Final 34
Deleted 1
Soon to be Proposed 1
Non NPL 68
Total 107

Top of page


Current Site Work

Ongoing Removals: 19, Active TAGs: 6, Ongoing RI/FS Actions: 82, Ongoing RDs: 18, Ongoing RAs: 53, Ongoing O&M: 47

Top of page


Completed Site Work

Removed Comps: 486, Decision Documents: 685, RD Comps: 234, RA Comps: 284, OPS: 45, 5 Year Reviews: 68, Partial Deletions: 5

Top of page


BRAC Federal Facility Site Cleanup Pipeline

BRAC Facilities: 107, BRAC Facilities with IAGs: 34, Active RABs: 68, Final Remedy Selected: 26, All Construction Completed: 10, Deleted Facility: 1

Top of page


Interagency Agreements (IAGs)

% of BRAC Federal Facilities with Completed IAGs

Federal Agencies that have not acheived 100% of their IAGs/FFAs
Agency # w/ IAG Total # Percent
Navy 9 35 25.7%
Army 11 40 27.5%
Air Force 12 29 41.4%
Dept. of Defense 0 1 0.0%
Federal Agencies that have acheived 100% of their IAGs/FFAs
Agency # w/ IAG Total # Percent
DLA 2 2 100.0%

Top of page


Remedial Actions and Removal Actions with Institutional Controls at BRAC Facilities

Remedial Actions: 169, Removals: 8

Note: There are 47 BRAC Federal Facilities with Institutional Controls.

Top of page


Status of Remedies Requiring Monitoring at BRAC Facilities

Total Number of Sites with Completed 5 Year Reviews = 39
(Latest Protectivness Statment at Site)

Protective: 15, Will Be Protective at Remedy Complete: 5, Protective in the Short Term: 11, Not Protective: 1, Protectiveness Deferred: 5, Complete: 2

Note: In the second quarter of FY 2005, EPA implemented a change in the way 5 Year Review data is recorded.

Top of page


Environmental Indicators Status for Final NPL BRAC Federal Facilities

(Total Facilities = 35)

Human Exposure Controlled: 29, Human Exposure Insufficient Data: 5, Human Exposure Not Controlled: 1, Groundwater Controlled: 21, Groundwater Insufficient Data: 6, Groundwater Not Controlled: 7, Not a GW Site: 1

Note: 57% of Facilities have both Human Exposure and Groundwater controlled; 3% of Facilities have neither Human Exposure nor Groundwater controlled.

Top of page


BRAC Federal Facilities Which Are Sitewide Ready for Anticipated Use

7