Jump to main content.


Escambia Wood - Pensacola

Photos/Multimedia

Aerial view of site June 2010
- Additional Site Photos
- 2008 Site Video
- 2010 Site Video

Additional Resources
Site Summary Profile
EPA ID: FLD008168346
Location: Pensacola, Escambia County, FL
Lat/Long: 30.455300, -87.231700
Congressional District: 01
NPL Status: Proposed: 08/23/1994; Final: 12/16/1994
Affected Media: Soil
Cleanup Status: Early Action Initiated/Completed, Construction Underway. Physical cleanup is almost complete and construction of soil contamination remedy is scheduled for completion in 2009
Site Reuse/Redevelopment: Anticipated commercial or light industrial use
Site Manager: Erik Spalvins (spalvins.erik@epa.gov)


Site Background

The 26-acre Escambia Wood Treating Company site in Pensacola, Florida is an abandoned wood preserving facility. From 1942 until its closing in 1982, Escambia manufactured wood products treated with creosote and pentachlorophenol (PCP). Contamination from Escambia activities has impacted 96 acres of land and a ground water plume that extends approximately 1.3 miles from the site.

The Escambia Wood Treating Company filed for bankruptcy and abandoned the site in 1991, prior to the first removal action.

Top of page

Threats and contaminants

Creosote, pentachlorophenol (PCP), polyaromatic hydrocarbons (PAHs), and dioxin are the main contaminants found on the site. Properties adjacent to the site include residential lands where PAH and dioxin contamination attributable to the site has been identified. Primary contaminants in the ground water are PCP and naphthalene.

Top of page

Site Cleanup Plan

The cleanup plan for the Escambia site covered two operable units (OUs): OU-1 (soil) and OU-2 (ground water).

An interim cleanup plan was selected for OU-1 in 1997. Major components of the interim plan included:

The Record of Decision for OU-1 was issued in 2006. Major components of the cleanup approach included:

The Record of Decision for OU-2 was issued in 2008. Major components of the cleanup approach included:

Top of page

Clean-up Progress

The Escambia site is currently being cleaned up – permanent relocation of impacted households is nearing completion, soil source material containment is underway, and ground water treatment is in planning stages.

From 1991 to 1992, EPA excavated 225,000 cubic yards of contaminated material and stored it under a secure cover on-site.

The interim remedy began in 1997 and consisted of relocation of 358 households. The government acquired 158 single family homes, a 200-unit apartment complex, and 11 vacant residential lots, successfully relocating over 500 persons to comparable replacement housing. Demolition of the properties and disposal of associated waste materials were completed in 2005. In 2006, an additional 46 households were identified as being directly impacted by contamination. Permanent relocation of these households began in December 2006 and was completed in 2009.

Construction of the remedy for OU-1 (soil) began in September 2007, and the earthwork portion of the project was completed in January 2010. More than 500,000 cubic yards of contaminated soil were buried in a lined containment cell on site. The remaining construction activities include establishing vegetation, replacing a sewer line, and treating water draining from the containment cell. Approximately 10.2% of the total cost of the cleanup was funded by the American Recovery and Reinvestment Act (ARRA). A total of $3.5 million of ARRA funds was provided to the project and was used to pay EPA’s contractor and local subcontractors, and to provide supplies for construction. EPA’s contractor has reported that 79.25 jobs were created with the ARRA funds. 

Technical planning to implement the selected remedy for OU-2 (ground water) is currently underway.

Top of page

Enforcement Activities


Site cleanup activities are being led primarily by EPA.

Top of page

Community Involvement

EPA has conducted a range of community involvement activities at the site to solicit community input and to ensure that the public remains informed about site activities throughout the site cleanup process. Outreach activities have included site fact sheets (found below), public notices, and information meetings on cleanup progress and activities.

In 1999, EPA entered into a cooperative agreement with the Escambia County Community Redevelopment Agency to learn about what future land uses the community anticipated having from the site. The conceptual redevelopment plan designed by the County was considered in the Remedial Investigation/Feasibility Study for OU-1, and cleanup design for OU-1 was completed in collaboration with the community.

Top of page

Future Work

Implementation of the OU-1 (soil) cleanup approach is on-going.

Once remedy design is complete, construction will commence for the OU-2 (ground water) remedy.

Top of page

Site Documents

Site Repository

For more information or to view any site-related documents, please visit the site information repository at the following location. As new documents are generated, they will be placed in the information repository for public information.

West Florida Regional Library
200 West Gregory St.
Pensacola, FL 32501

For documents not available on the website, please contact the Region 4 Freedom of Information Office.

Top of page


Local Navigation



Jump to main content.