Jump to main content.


Leonard Chemical Company, Inc.

Additional Resources
Site Summary Profile
EPA ID: SCD991279324
Location: Rock Hill, York County, SC
Lat/Long: 34.851660, -080.904160
Congressional District: 05
NPL Status: Proposed: 09/08/83; Final: 9/21/84
Affected Media: Ground water, Liquid Waste, Soil
Cleanup Status: RD/RA Underway - Physical cleanup activities have started.
Human Exposure Under Control: Yes
Groundwater Migration Under Control: No
Sitewide Ready for Anticipated Use: No
Site Reuse/Redevelopment: Site is not in use potential for industrial or residential reuse
Site Manager: Deborah Cox (cox.deborah@epa.gov)


Current Site Status

The Leonard Chemical Co., Inc. site includes the area where Leonard Chemical Company operated a waste treatment facility from the late 1960s to 1982. The Environmental Protection Agency (EPA) placed the Site on the National Priorities List (NPL) in 1984 because of contaminated soil, ground water and liquid waste resulting from facility operations. EPA, the South Carolina Department of Health and Environmental Control (SCDHEC) and the site’s potentially responsible parties (PRPs) have investigated site conditions and taken steps to clean up the Site in order to protect people and the environment from contamination. Site contamination does not currently threaten people living and working near the Site. By treating ground water, EPA, SCDHEC and the site’s PRPs continue to protect people and the environment from site contamination.

Top of page

Site Location and Background

The 7-acre site is located in a rural area of Rock Hill on Cureton Ferry Road, near Highway 697, approximately one half-mile east of Catawba, York County, South Carolina. A rail line borders the Site to the north, industrial land uses border the Site to the south, Ferry Branch Creek borders the Site to the east, and undeveloped land borders the Site to the west. The site’s broader surroundings include agricultural and industrial land uses and forested areas.

The Site includes the area where Leonard Chemical Company operated a hazardous waste treatment facility from the late 1960s to 1982. Operations included separating wastes through boiling and placing residues from this process in various locations on site. Operations left approximately 3,400 drums and 11,500 gallons of chemicals on site, including solvents, printing inks, polyester solids, wastes resulting from solvent boiling and filters for paint, water and fiberglass. In 1984, EPA listed the Site on the NPL.

The Site is not in use. Fencing surrounds the site and restricts access. Following cleanup activities, the site will be able to support industrial and residential uses.

Top of page

Threats and Contaminants

Site investigations found contamination in soil, ground water and liquid waste that could potentially harm people in the area. Contamination resulted from operations and waste handling practices at the site. Contaminants of concern include metals, polycyclic aromatic hydrocarbons (PAHs) and volatile organic compounds (VOCs).

Top of page

Investigation and Cleanup Responsibility / Oversight

The site’s PRPs lead site investigation and cleanup activities, with oversight provided by EPA and SCDHEC.

Top of page

Site Cleanup Plan

In 1990, EPA issued a cleanup plan (a Record of Decision, or ROD) for the Site. The plan included the following activities:

In 2003, EPA issued an Explanation of Significant Differences (ESD) to update the remedial goals (RGs) for subsurface soil constituents based on site-specific leach tests conducted by the PRPs and reviewed by EPA.  The potential for this change was noted in the ROD.

Summaries of site cleanup approaches are also available online in key site cleanup documents, including the ROD.

Top of page

Cleanup Progress

In 1983, the PRPs retained a contractor to remove wastes from the site, under the oversight of the SCDHEC. Approximately 80% of surface wastes were removed in this removal action.

In 1984, the PRP group conducted a remedial investigation (RI) of the Site including monitoring well installation and sampling, subsurface soil sampling, and stream and sediment sampling. Additional field work was conducted to determine the extent of ground-water contamination both on and off site.

The final remedial design (RD) for phase I was completed in March 2009 and a remedial action (RA) workplan was submitted to EPA in summer 2009. In July 2010 18” of surface soil was excavated from three locations referred to as Area 1, Area 2, and Area 3.  These areas were backfilled with clean soil.  In September 2010 Phase I of the Air Sparge (AS)/Soil Vapor Extraction (SVE) System was installed to include a treatment fence in the southeastern corner of the Site. The first Quarterly Performance Monitoring Event was December 2010/ January 2011. The 10th Quarterly Performance Monitoring Event was conducted March 2013.  This event is currently being utilized as the basis of design for Phase II expansion of the AS/SVE System.  RD is scheduled to be complete September 2013.  Phase II RA is scheduled to commence in December 2013.

Top of page

Enforcement Activities

EPA negotiated legal agreements with the Site’s PRPs to investigate and clean up the site. The PRPs continue to fund site cleanup, monitoring and oversight activities.

Under a 1983 court order, Leonard Chemical Company cannot resume site operations without prior approval of SCDHEC.

On December 13, 1990, EPA issued an Administrative Order on Consent (AOC) to the PRPs for performance of a Remedial Investigation and Feasibility Study (RI/FS).

In July 1991, a Consent Decree (CD) was entered by the Court triggering the initialization of field investigations by PRP contractors.

In November 2004, a CD was entered with the Leonard Chemical PRP Group for RD/RA.

March 2013, an AOC was signed between the EPA and the PRPs that did not sign onto the 2004 CD, to settle the EPA's past cost.

The ROD online provides additional information on specific legal agreements for the site.

Top of page

Community Involvement

EPA is working with the community and its state partner to develop a long-term cleanup plan for the site, reflecting the Agency’s commitment to safe, healthy communities and environmental protection. Community engagement and public outreach are core components of EPA program activities.

EPA plans to conduct a range of community involvement activities to solicit community input and to make sure the public remains informed about site activities throughout the cleanup process. Outreach efforts include public notices, interviews and public meetings on cleanup activities and updates.

Top of page

Future Work

The site’s PRPs begin the phase II expansion of the soil and groundwater treatment system in the fall of 2013. The PRPs will install additional wells on site for monitoring and treatment purposes.

Top of page

Additional Information

EPA keeps additional site documents and information in a site information repository at the location below. EPA also posts site documents, when available, on EPA’s CERCLIS Site Profile page. For documents not available on the website, please contact the Region 4 Freedom of Information Office.

Site Repository

York County Library
138 E. Black Street
Rock Hill, SC 29731

Top of page


Local Navigation



Jump to main content.