Capability to maintain adequate oversight of response actions, including, but not limited
to: assuring and controlling the quality of data sampling and analysis, risk
characterizations or assessments, and design and implementation of remedies; monitoring
project progress, including enforcing timelines; and communicating with EPA program
managers.
It is also necessary to take into consideration the performance history of the state relative
to its state cleanup authorities.
2. Community Involvement
Additionally, while the Federal lead cleanup agency has responsibility for providing
community involvement under CERCLA, states, where they are the designated lead regulator,
should work to promote input from communities in a manner that fosters community
participation in decisions regarding response actions at sites. As recommended in the Final
Report of the Federal Facilities Environmental Restoration Dialogue Committee (FFERDC)
(April 1996), community participation will be facilitated by the establishment of RABs/SSABs
by the federal agencies in coordination with the state. The state should take appropriate steps to
ensure that the affected community and other affected parties (e.g., communities downstream
from the site, Natural Resource Trustees, etc.), as appropriate, are kept informed of any
differences in timetables or criteria that may result from integrating the federal CERCLA process
with a state program authorized under RCRA or other state cleanup law process and other
information relating to the cleanup. Where EPA, the state, and the lead cleanup agency are
entering into a lead regulator agreement that is not currently captured in an existing IAG,
adequate public notice must be provided concerning the lead regulator agreement.
Similarly, under any lead regulator agreement, the federal agency is responsible for
funding technical assistance grant (TAG)-like grants and services. EPA may fund TAGs at NPL
sites. EPA may delegate responsibility for overseeing and issuing TAGs to states under the
CERCLA framework (40 CFR 35.4015(b)). The state should also document all of its
interactions with the community and inform EPA and the federal lead cleanup agency of any
possible opposition to the cleanup.
3. Consultation With EPA
In order for EPA to implement its CERCLA responsibilities, EPA should ensure that
lead regulator agreements provide for a meaningful consultation role for EPA and the federal
lead cleanup agency to ensure that cleanups are occurring in a timely fashion and will be
consistent with the final remedy at the facility. EPA should also ensure that lead regulator
agreements provide for a joint scoping process that results in agreement with EPA and the lead
cleanup agency on end-point remediation objectives and the data required to answer the
questions necessary to meet cleanup objectives. Over time and based on cleanup program
maturity, state lead regulator oversight responsibilities can be adjusted to reflect the state's
capability and resources. Conditions and expectations of the consultation role should be
documented in the state/EPA lead regulator agreement.
B. EPA Reservation Of Rights
EPA is committed to developing and implementing lead regulator agreements. Where a
state is the lead regulator, EPA must still exercise its CERCLA obligations under section 120,
including concurrence on remedies proposed by the federal lead cleanup agency and the state.
Therefore, EPA must reserve its right to ensure that the cleanup is consistent with the
requirements for a final remedy under CERCLA and, if appropriate, to delete the site from the
NPL. Provided that effective consultation has been occurring during the cleanup process, EPA
does not anticipate the need for requiring additional action when it receives the proposed Record
of Decision for concurrence.
As noted above, where a state is the lead regulator for a cleanup, EPA will normally take
an active role in the cleanup if: 1) proposed remedies are not protective; 2) EPA needs to perform
statutory or regulatory obligations (e.g., NPL deletion procedures or remedy concurrence); 3)
state oversight is not leading to a timely response action; or 4) the state or the federal lead
cleanup agency that manages the facility requests EPA involvement or action.
Where a state is the lead regulator, as with any cleanup, EPA will continue to reserve any
statutory authorities it may have available to take enforcement actions with respect to particular
sites or under certain circumstances. EPA also recognizes that states may also reserve their
enforcement and other authorities with respect to cleanup or other activities at particular sites.
V. SUMMARY
We encourage you to continue to expand your efforts in implementing the lead regulator
policy at the Federal facilities in your Regions. In addition to this policy, we recommend that
you refer to the following guidance documents when choosing a lead regulator: "Coordination
Between RCRA Corrective Action and Closure and CERCLA Site Activities," Steve A. Herman,
Assistant Administrator, Office of Enforcement and Compliance Assurance, and Elliott P. Laws,
Assistant Administrator, Office of Solid Waste and Emergency Response, September 24, 1996,
and "Guidance on Improving Communication to Achieve Collaborative Decision-Making at
Department of Energy Sites," Steve A. Herman, Assistant Administrator, Office of Enforcement
and Compliance Assurance, Tim Fields, Acting Assistant Administrator, Office of Solid Waste
and Emergency Response, and Alvin L. Alm, Assistant Secretary for Environmental
Management, U.S. Department of Energy, June 16, 1997. If you have questions on the issues
discussed in this memorandum regarding remedy selection or response actions, please contact the
Federal Facilities Restoration and Reuse Office, at (202) 260-9924, or if you have specific
questions regarding IAGs or enforcement issues, please contact the Federal Facilities
Enforcement Office at (202) 564-2510.
VI. DISCLAIMER
This policy and internal procedures adopted for implementation are intended solely as
policy for employees of the US EPA. Such policy and procedures do not constitute rule making
by the Agency and do not create legal obligations. The extent to which EPA applies this policy
will depend on the facts of each case.
Attachment
cc: James Woolford, Federal Facilities Restoration and Reuse Office
Craig Hooks, Federal Facilities Enforcement Office
RCRA/CERCLA National Program Managers
Sherri Goodman, Department of Defense
Ellsie Munsell, Department of the Navy
Thomas (Tad) McCall, Jr., Department of the Air Force
Raymond Fatz, Department of the Army
Jan Reitman, Defense Logistics Agency
Lois Schiffler, Department of Justice
Al Alm, Department of Energy
Willie Taylor, Department of the Interior
Ed Cohen, Department of the Interior
Blake Velde, United States Department of Agriculture
Federal Facilities Leadership Council
Defense Environmental Response Task Force
Association of State and Territorial Solid Waste Management Officials
National Association of Attorneys General
National Governors Association
Environmental Council of States
RAB/SSAB Co-chairs
National Tribal Environmental Council
Inter-tribal Council of Arizona
National Congress of American Indians
Attachment I
.
LEAD REGULATOR POLICY IN PRACTICE
In advance of the Lead Regulator Policy, a number of states and EPA Regions have
successfully negotiated and implemented site-specific lead regulator agreements. For example, a
lead regulator agreement was recently reached at the Rocky Flats Environmental Technology
Site
(RFETS), a Department of Energy site in Colorado that is listed on the NPL.
In January 1991, DOE entered into an IAG and Compliance Order on Consent with EPA
and Colorado for required CERCLA remedial action and RCRA corrective action at RFETS.
The IAG incorporated a regulatory approach that was based on the objective of CERCLA and
RCRA (including state hazardous waste law) integration. A lead regulatory agency was assigned
(with the other agency being the support regulatory agency) for most of the sites's 16 designated
operable units, but 3 operable units were assigned joint-EPA/state lead. Despite the lead
regulator assignment, in the 1991 IAG, each regulatory agency retained approval authority for its
requirements in each operable unit. Therefore, all decision documents were subject to comment
and approval by both EPA and the state. The support regulatory agency's comments were
submitted to the lead agency, but provided to RFETS unedited for RFETS's response. Thus,
there was a duplication of effort by the state and EPA and the requirement for RFETS to deal
with two regulators on nearly every deliverable that was unnecessarily time-consuming and
confusing. RFETS was at times uncertain whether EPA's and the state's comments or concerns
were consistent, and at times the comments appeared to conflict, compounding coordination
problems. Although there were a number of other reasons resulting in the parties' decision to
renegotiate the 1991 IAG, it was agreed that an approach resulting in a single lead regulator in
each operable unit with full regulatory approval authority to the maximum extent possible
presented opportunities to streamline work.
The renegotiated agreement, effective July 1996, is known as the Rocky Flats Cleanup
Agreement (RFCA). The RFCA regulatory approach coordinates RCRA corrective action and
CERCLA remediation requirements. Under RFCA, the RFETS NPL site is divided into two
areas: the Industrial Area, for which the state is the lead regulator; and the Buffer Zone, for
which
EPA is the lead regulator. Cleanup of the Industrial Area is regulated under applicable state law
and where state law is not applicable (e.g., radioactive materials) under CERCLA requirements.
The Buffer Zone is being cleanup up under CERCLA. Under RFCA, Colorado carries out EPA's
CERCLA authority in the Industrial Area, except where such authority is statutorily reserved to
EPA. Except for certain site-wide decisions, the lead regulator has the sole oversight and
approval authority in its area, and it is responsible to keep the other regulatory agency informed
and to obtain that agency's concurrence if and when required under the RFCA. Therefore, to the
maximum extent practicable, DOE interfaces with only one regulator and follows one regulatory
regime in each of the two areas. The RFCA approach so far allows for shorter turnaround on
document approvals and has markedly improved RFETS ability to accelerate risk reducing
removal actions.
Other examples of successful implementation of the lead regulator concept include the
DOE site Hanford, in the State of Washington, and the Navy facility Port Hadlock, also in
Washington. In the summer of 1995, management from EPA, DOE and the State of Washington
Department of Ecology (Ecology) met to examine ways of fundamentally improving the cleanup
effort at Hanford so that it would be more efficient and cost effective. To help accomplish those
goals, the three parties agreed to adopt a single regulator concept where only one regulatory
agency would generally be involved in the day to day oversight and decision making on
individual cleanup activities. In the past, the regulatory agency acting in the support rather than
lead role had often invested significant resources to participate in oversight of DOE and its
contractors. The IAG was amended to require EPA and the state to designate a single lead
regulatory agency (LRA) for each operable unit and RCRA Treatment, Storage, and Disposal
(TSD) unit at the site. The LRA is empowered to make all regulatory decisions at those units
within the scope of their authority. The state has an authorized RCRA program and is designated
as the lead for all the RCRA units, as well as a number of the CERCLA operable units. EPA
retains responsibility for selecting remedial actions at state lead CERCLA operable units as
required by section 120 of CERCLA. However, under the lead regulator agreement, EPA relies
on the state to do all the regulatory oversight work necessary to develop a recommended
remedial
alternative that EPA can approve.
EPA Region 10 and Ecology executed an agreement in 1994 entitled "Superfund
Management in Washington." Under that agreement, Port Hadlock was designated a state lead
federal facility site, and Ecology has primary responsibility for the review and approval of work
plans and other deliverables and for oversight of remedial action. After completion of a
Remedial Investigation/Feasibility Study (RI/FS) by the Navy with state oversight and issuance
of the Record of Decision (ROD), an IAG was signed by EPA, the Navy and the State of
Washington. The IAG provides that the state shall be responsible for approving workplans and
overseeing implementation of the IAG without EPA participation in accordance with the
EPA/state agreement. Any disputes are resolved by the state unless the Navy determines that the
dispute has national policy implications, in which case the dispute can be elevated to the EPA
Administrator for resolution.
At the U.S. DOE site in Fernald, Ohio, both EPA and the state are working together to
utilize a team approach for conducting oversight of the DOE cleanup. Both the state and EPA
review all documents and submit comments to DOE. The state takes the lead on most field
projects, since the site is close to the state office. Both the state and EPA attend technical and
public meetings. This unified regulator approach increases stakeholder comfort toward oversight
of the facility. DOE and EPA have agreed to this arrangement for the Fernald site in an
Amended Consent Agreement under CERCLA Sections 120 and 106(a).
The relationship between EPA and the Ohio EPA in handling oversight originated as
EPA's authority over DOE's management of mixed waste and other RCRA waste activities
developed in the late 1970's. Both regulatory agencies worked together in an integrated fashion
to handle field oversight and provide technical review of documents, while implementing the
regulations. This working relationship between EPA and Ohio EPA carried over into the 1990
CERCLA agreement as both regulatory agencies work together to assure DOE implements
remedies according to CERCLA and in the best interest of the community. The regulators
frequently discuss who will review certain aspects of technical documents, or conduct field
oversight. The team regulator approach has worked successfully for years and will continue to
be
implemented in the future at the Fernald site. Therefore, in areas where the state and EPA have
established a good working relationship and communicate regularly, utilizing a team
"synergistic" approach may be the appropriate approach for conducting oversight.
1.
See, "Coordination between RCRA Corrective Action and Closure and CERCLA Site
Activities," OSWER Directive 9200.0-25, September 24, 1996.
Return to Document
2.
For the purposes of this policy, "federal lead cleanup agency" is defined as the federal agency
that owns or operates the federal facility.
Return to Document